Office Relocation: IT Infrastructure Move
We move the entire IT infrastructure of an office relocation. The new site is prepared and tested before anything is unplugged, the move itself is executed over one weekend, and the business works normally on Monday. Preparation typically requires 1 to 2 weeks before the move date itself.
Who it is for
- Businesses changing premises that cannot absorb downtime
- Companies with a server, NAS or phone system to relocate
- Organisations wanting to fix what has been working marginally
- Sites where the move must happen outside working hours
When we are NOT the right choice
- If the new site cannot be prepared before the move date
- If a same-day move with no preparation is requested
- If there is no access to the systems for an inventory
PROCESS
The process
Indicative times from signature of the proposal, subject to hardware availability. Every project is shaped to the size and the needs of the client.
01Infrastructure inventory
We record what exists, what moves, what is replaced, and which dependencies exist with providers and applications.Time: 2-5 working daysDeliverable: Register of equipment, circuits and dependencies
02Preparation of the new site
Cabling, rack, network and wireless are built and tested before any equipment moves. The internet circuit is ordered early, because it depends on the provider.Time: 1-2 weeksDeliverable: Cabling, rack and network ready
03Sequenced move plan
We define the shutdown and reconnection sequence, who does what and when, and the rollback plan if something does not go as expected.Time: Before the move dateDeliverable: Plan with sequence, timings and owners
04Move over one weekend
The move and reconnection happen outside working hours so Monday is a normal working day. We test real workflows, not just connectivity.Time: One weekendDeliverable: Reconnected and tested systems
05First working day on site
We are present on the first operating day for whatever arises, and hand over updated documentation for the new site.Time: On the first working dayDeliverable: On-site attendance and updated register
| What is included | What is not included |
|---|---|
| Infrastructure and dependency inventory | Furniture and general removals |
| Network preparation at the new site | Builders work and electrical installation |
| Move plan with sequence and timings | Provider delays in activating circuits |
| Disconnection, transport and reconnection of systems | Repair of equipment already in a failed state |
| Testing of real workflows after reconnection | |
| On-site attendance on the first working day |
Technology and equipment
- MikroTik RouterOS
- Ubiquiti UniFi
- Omada / TP-Link
- Synology
- FreePBX / Asterisk
- Microsoft 365
From practice
In every relocation the critical path is the same and it is rarely technical: it is the activation of the internet circuit at the new site. If the order goes in late, no amount of planning accelerates it.
That is why preparation starts weeks ahead and the move itself is the last, shortest part of the work. When the new site has already been tested, one weekend is enough.
Prerequisites
- Access to the new site at least two weeks in advance
- An internet circuit ordered early for the new site
- Access to systems and management credentials
- An agreed out of hours move window
Cost
Quoted as a project, with preparation of the new site and the move itself itemised separately. Out of hours work is shown as its own line, so the cost of the weekend window is explicit rather than buried.
We do not publish a price list. Every proposal follows a site survey and separates hardware from labour.
What moves the cost
- Number of workstations and systems to relocate
- How much infrastructure must be built from scratch at the new site
- Whether a server or phone system carries continuity requirements
- How tight the available move window is
Frequently asked questions
How much downtime will we have?
When should preparation start?
Do you move the server as well?
Can we upgrade at the same time?
NEXT STEP
Plan your IT infrastructure move
We inventory what moves, prepare the new site, and deliver a move plan with sequence, timings and named owners.