Office Relocation: IT Infrastructure Move

We move the entire IT infrastructure of an office relocation. The new site is prepared and tested before anything is unplugged, the move itself is executed over one weekend, and the business works normally on Monday. Preparation typically requires 1 to 2 weeks before the move date itself.

Who it is for

  • Businesses changing premises that cannot absorb downtime
  • Companies with a server, NAS or phone system to relocate
  • Organisations wanting to fix what has been working marginally
  • Sites where the move must happen outside working hours

When we are NOT the right choice

  • If the new site cannot be prepared before the move date
  • If a same-day move with no preparation is requested
  • If there is no access to the systems for an inventory

PROCESS

The process

Indicative times from signature of the proposal, subject to hardware availability. Every project is shaped to the size and the needs of the client.

  1. 01Infrastructure inventory

    We record what exists, what moves, what is replaced, and which dependencies exist with providers and applications.Time: 2-5 working daysDeliverable: Register of equipment, circuits and dependencies

  2. 02Preparation of the new site

    Cabling, rack, network and wireless are built and tested before any equipment moves. The internet circuit is ordered early, because it depends on the provider.Time: 1-2 weeksDeliverable: Cabling, rack and network ready

  3. 03Sequenced move plan

    We define the shutdown and reconnection sequence, who does what and when, and the rollback plan if something does not go as expected.Time: Before the move dateDeliverable: Plan with sequence, timings and owners

  4. 04Move over one weekend

    The move and reconnection happen outside working hours so Monday is a normal working day. We test real workflows, not just connectivity.Time: One weekendDeliverable: Reconnected and tested systems

  5. 05First working day on site

    We are present on the first operating day for whatever arises, and hand over updated documentation for the new site.Time: On the first working dayDeliverable: On-site attendance and updated register

What is includedWhat is not included
Infrastructure and dependency inventoryFurniture and general removals
Network preparation at the new siteBuilders work and electrical installation
Move plan with sequence and timingsProvider delays in activating circuits
Disconnection, transport and reconnection of systemsRepair of equipment already in a failed state
Testing of real workflows after reconnection
On-site attendance on the first working day

Technology and equipment

  • MikroTik RouterOS
  • Ubiquiti UniFi
  • Omada / TP-Link
  • Synology
  • FreePBX / Asterisk
  • Microsoft 365

From practice

In every relocation the critical path is the same and it is rarely technical: it is the activation of the internet circuit at the new site. If the order goes in late, no amount of planning accelerates it.

That is why preparation starts weeks ahead and the move itself is the last, shortest part of the work. When the new site has already been tested, one weekend is enough.

Prerequisites

  • Access to the new site at least two weeks in advance
  • An internet circuit ordered early for the new site
  • Access to systems and management credentials
  • An agreed out of hours move window

Cost

Quoted as a project, with preparation of the new site and the move itself itemised separately. Out of hours work is shown as its own line, so the cost of the weekend window is explicit rather than buried.

We do not publish a price list. Every proposal follows a site survey and separates hardware from labour.

What moves the cost

  • Number of workstations and systems to relocate
  • How much infrastructure must be built from scratch at the new site
  • Whether a server or phone system carries continuity requirements
  • How tight the available move window is

Frequently asked questions

How much downtime will we have?

The objective is no lost working time. The move is scheduled over a weekend with the new site already built and tested, so Monday starts normally.

When should preparation start?

Typically 1 to 2 weeks before the move, and earlier if new cabling is required. The critical path is almost always the provider activating the internet circuit.

Do you move the server as well?

Yes. Server and NAS are moved with a sequenced plan and a verified recent backup taken before disconnection. Nothing is unplugged without that step.

Can we upgrade at the same time?

A relocation is the best moment to fix what has been working marginally, because the equipment is coming out anyway. We propose it as a separate line in the quotation.

NEXT STEP

Plan your IT infrastructure move

We inventory what moves, prepare the new site, and deliver a move plan with sequence, timings and named owners.

GET IN TOUCH

Tell us what you need

Four fields. An engineer replies, not a sales desk.

Fields marked * are required.

By sending this form you accept the processing of your details under our Privacy Policy.